chamiakJ 8f913b0f4e Add task progress tracking methods documentation and enhance progress update logic
- Introduced a new markdown file detailing task progress tracking methods: manual, weighted, and time-based.
- Updated backend logic to include complete ratio calculations for tasks.
- Improved socket command for task progress updates, enabling recursive updates for ancestor tasks.
- Enhanced frontend components to reflect progress changes based on the selected tracking method, including updates to task display and progress input handling.
- Added support for manual progress flag in task model to facilitate accurate progress representation.
2025-05-02 07:37:40 +05:30

9.9 KiB

Task Progress Tracking Methods in WorkLenz

Overview

WorkLenz supports three different methods for tracking task progress, each suitable for different project management approaches:

  1. Manual Progress - Direct input of progress percentages
  2. Weighted Progress - Tasks have weights that affect overall progress calculation
  3. Time-based Progress - Progress calculated based on estimated time vs. time spent

These modes can be selected when creating or editing a project in the project drawer.

1. Manual Progress Mode

This mode allows direct input of progress percentages for individual tasks without subtasks.

Implementation:

  • Enabled by setting use_manual_progress to true in the project settings
  • Progress is updated through the on-update-task-progress.ts socket event handler
  • The UI shows a manual progress input slider in the task drawer for tasks without subtasks
  • Updates the database with progress_value and sets manual_progress flag to true

Calculation Logic:

  • For tasks without subtasks: Uses the manually set progress value
  • For parent tasks: Calculates the average of all subtask progress values
  • Subtask progress comes from either manual values or completion status (0% or 100%)

Code Example:

// Manual progress update via socket.io
socket?.emit(SocketEvents.UPDATE_TASK_PROGRESS.toString(), JSON.stringify({
  task_id: task.id,
  progress_value: value,
  parent_task_id: task.parent_task_id
}));

Showing Progress in Subtask Rows

When manual progress is enabled in a project, progress is shown in the following ways:

  1. In Task List Views:

    • Subtasks display their individual progress values in the progress column
    • Parent tasks display the calculated average progress of all subtasks
  2. Implementation Details:

    • The progress values are stored in the progress_value column in the database
    • For subtasks with manual progress set, the value is shown directly
    • For subtasks without manual progress, the completion status determines the value (0% or 100%)
    • The task view model includes both progress and complete_ratio properties

Relevant Components:

// From task-list-progress-cell.tsx
const TaskListProgressCell = ({ task }: TaskListProgressCellProps) => {
  return task.is_sub_task ? null : (
    <Tooltip title={`${task.completed_count || 0} / ${task.total_tasks_count || 0}`}>
      <Progress
        percent={task.complete_ratio || 0}
        type="circle"
        size={24}
        style={{ cursor: 'default' }}
      />
    </Tooltip>
  );
};

Task Progress Calculation in Backend:

// From tasks-controller-base.ts
// For tasks without subtasks, respect manual progress if set
if (task.manual_progress === true && task.progress_value !== null) {
  // For manually set progress, use that value directly
  task.progress = parseInt(task.progress_value);
  task.complete_ratio = parseInt(task.progress_value);
} 

2. Weighted Progress Mode

This mode allows assigning different weights to subtasks to reflect their relative importance in the overall task or project progress.

Implementation:

  • Enabled by setting use_weighted_progress to true in the project settings
  • Weights are updated through the on-update-task-weight.ts socket event handler
  • The UI shows a weight input for subtasks in the task drawer
  • Default weight is 100 if not specified

Calculation Logic:

  • Progress is calculated using a weighted average: SUM(progress_value * weight) / SUM(weight)
  • This gives more influence to tasks with higher weights
  • A parent task's progress is the weighted average of its subtasks' progress

Code Example:

// Weight update via socket.io
socket?.emit(SocketEvents.UPDATE_TASK_WEIGHT.toString(), JSON.stringify({
  task_id: task.id,
  weight: value,
  parent_task_id: task.parent_task_id
}));

3. Time-based Progress Mode

This mode calculates progress based on estimated time vs. actual time spent.

Implementation:

  • Enabled by setting use_time_progress to true in the project settings
  • Uses task time estimates (hours and minutes) for calculation
  • No separate socket handler needed as it's calculated automatically

Calculation Logic:

  • Progress is calculated using time as the weight: SUM(progress_value * estimated_minutes) / SUM(estimated_minutes)
  • For tasks with time tracking, estimated vs. actual time can be factored in
  • Parent task progress is weighted by the estimated time of each subtask

SQL Example:

WITH subtask_progress AS (
    SELECT 
        CASE 
            WHEN manual_progress IS TRUE AND progress_value IS NOT NULL THEN 
                progress_value
            ELSE
                CASE 
                    WHEN EXISTS(
                        SELECT 1
                        FROM tasks_with_status_view
                        WHERE tasks_with_status_view.task_id = t.id
                        AND is_done IS TRUE
                    ) THEN 100
                    ELSE 0
                END
        END AS progress_value,
        COALESCE(total_hours * 60 + total_minutes, 0) AS estimated_minutes
    FROM tasks t
    WHERE t.parent_task_id = _task_id
    AND t.archived IS FALSE
)
SELECT COALESCE(
    SUM(progress_value * estimated_minutes) / NULLIF(SUM(estimated_minutes), 0),
    0
)
FROM subtask_progress
INTO _ratio;

Default Progress Tracking (when no special mode is selected)

If no specific progress mode is enabled, the system falls back to a traditional completion-based calculation:

Implementation:

  • Default mode when all three special modes are disabled
  • Based on task completion status only

Calculation Logic:

  • For tasks without subtasks: 0% if not done, 100% if done
  • For parent tasks: (completed_tasks / total_tasks) * 100
  • Counts both the parent and all subtasks in the calculation

SQL Example:

-- Traditional calculation based on completion status
SELECT (CASE
            WHEN EXISTS(SELECT 1
                        FROM tasks_with_status_view
                        WHERE tasks_with_status_view.task_id = _task_id
                          AND is_done IS TRUE) THEN 1
            ELSE 0 END)
INTO _parent_task_done;
            
SELECT COUNT(*)
FROM tasks_with_status_view
WHERE parent_task_id = _task_id
  AND is_done IS TRUE
INTO _sub_tasks_done;
            
_total_completed = _parent_task_done + _sub_tasks_done;
_total_tasks = _sub_tasks_count + 1; -- +1 for the parent task
            
IF _total_tasks = 0 THEN
    _ratio = 0;
ELSE
    _ratio = (_total_completed / _total_tasks) * 100;
END IF;

Technical Implementation Details

The progress calculation logic is implemented in PostgreSQL functions, primarily in the get_task_complete_ratio function. Progress updates flow through the system as follows:

  1. User Action: User updates task progress or weight in the UI
  2. Socket Event: Client emits socket event (UPDATE_TASK_PROGRESS or UPDATE_TASK_WEIGHT)
  3. Server Handler: Server processes the event in the respective handler function
  4. Database Update: Progress/weight value is updated in the database
  5. Recalculation: If needed, parent task progress is recalculated
  6. Broadcast: Changes are broadcast to all clients in the project room
  7. UI Update: Client UI updates to reflect the new progress values

This architecture allows for real-time updates and consistent progress calculation across all clients.

Associated Files and Components

Backend Files

  1. Socket Event Handlers:

    • worklenz-backend/src/socket.io/commands/on-update-task-progress.ts - Handles manual progress updates
    • worklenz-backend/src/socket.io/commands/on-update-task-weight.ts - Handles task weight updates
  2. Database Functions:

    • worklenz-backend/database/migrations/20250423000000-subtask-manual-progress.sql - Contains the get_task_complete_ratio function that calculates progress based on the selected method
    • Functions that support project creation/updates with progress mode settings:
      • create_project
      • update_project
  3. Controllers:

    • worklenz-backend/src/controllers/project-workload/workload-gannt-base.ts - Contains the calculateTaskCompleteRatio method
    • worklenz-backend/src/controllers/projects-controller.ts - Handles project-level progress calculations
    • worklenz-backend/src/controllers/tasks-controller-base.ts - Handles task progress calculation and updates task view models

Frontend Files

  1. Project Configuration:

    • worklenz-frontend/src/components/projects/project-drawer/project-drawer.tsx - Contains UI for selecting progress method when creating/editing projects
  2. Progress Visualization Components:

    • worklenz-frontend/src/components/project-list/project-list-table/project-list-progress/progress-list-progress.tsx - Displays project progress
    • worklenz-frontend/src/pages/projects/project-view-1/taskList/taskListTable/taskListTableCells/TaskProgress.tsx - Displays task progress
    • worklenz-frontend/src/pages/projects/projectView/taskList/task-list-table/task-list-table-cells/task-list-progress-cell/task-list-progress-cell.tsx - Alternative task progress cell
    • worklenz-frontend/src/components/task-list-common/task-row/task-row-progress/task-row-progress.tsx - Displays progress in task rows
  3. Progress Input Components:

    • worklenz-frontend/src/components/task-drawer/shared/info-tab/details/task-drawer-progress/task-drawer-progress.tsx - Component for inputting task progress/weight

Choosing the Right Progress Method

Each progress method is suitable for different types of projects:

  • Manual Progress: Best for creative work where progress is subjective
  • Weighted Progress: Ideal for projects where some tasks are more significant than others
  • Time-based Progress: Perfect for projects where time estimates are reliable and important

Project managers can choose the appropriate method when creating or editing a project in the project drawer, based on their team's workflow and project requirements.