- Introduced a new markdown file detailing task progress tracking methods: manual, weighted, and time-based.
- Updated backend logic to include complete ratio calculations for tasks.
- Improved socket command for task progress updates, enabling recursive updates for ancestor tasks.
- Enhanced frontend components to reflect progress changes based on the selected tracking method, including updates to task display and progress input handling.
- Added support for manual progress flag in task model to facilitate accurate progress representation.
2025-05-02 07:37:40 +05:30

244 lines
9.9 KiB
Markdown

# Task Progress Tracking Methods in WorkLenz
## Overview
WorkLenz supports three different methods for tracking task progress, each suitable for different project management approaches:
1. **Manual Progress** - Direct input of progress percentages
2. **Weighted Progress** - Tasks have weights that affect overall progress calculation
3. **Time-based Progress** - Progress calculated based on estimated time vs. time spent
These modes can be selected when creating or editing a project in the project drawer.
## 1. Manual Progress Mode
This mode allows direct input of progress percentages for individual tasks without subtasks.
**Implementation:**
- Enabled by setting `use_manual_progress` to true in the project settings
- Progress is updated through the `on-update-task-progress.ts` socket event handler
- The UI shows a manual progress input slider in the task drawer for tasks without subtasks
- Updates the database with `progress_value` and sets `manual_progress` flag to true
**Calculation Logic:**
- For tasks without subtasks: Uses the manually set progress value
- For parent tasks: Calculates the average of all subtask progress values
- Subtask progress comes from either manual values or completion status (0% or 100%)
**Code Example:**
```typescript
// Manual progress update via socket.io
socket?.emit(SocketEvents.UPDATE_TASK_PROGRESS.toString(), JSON.stringify({
task_id: task.id,
progress_value: value,
parent_task_id: task.parent_task_id
}));
```
### Showing Progress in Subtask Rows
When manual progress is enabled in a project, progress is shown in the following ways:
1. **In Task List Views**:
- Subtasks display their individual progress values in the progress column
- Parent tasks display the calculated average progress of all subtasks
2. **Implementation Details**:
- The progress values are stored in the `progress_value` column in the database
- For subtasks with manual progress set, the value is shown directly
- For subtasks without manual progress, the completion status determines the value (0% or 100%)
- The task view model includes both `progress` and `complete_ratio` properties
**Relevant Components:**
```typescript
// From task-list-progress-cell.tsx
const TaskListProgressCell = ({ task }: TaskListProgressCellProps) => {
return task.is_sub_task ? null : (
<Tooltip title={`${task.completed_count || 0} / ${task.total_tasks_count || 0}`}>
<Progress
percent={task.complete_ratio || 0}
type="circle"
size={24}
style={{ cursor: 'default' }}
/>
</Tooltip>
);
};
```
**Task Progress Calculation in Backend:**
```typescript
// From tasks-controller-base.ts
// For tasks without subtasks, respect manual progress if set
if (task.manual_progress === true && task.progress_value !== null) {
// For manually set progress, use that value directly
task.progress = parseInt(task.progress_value);
task.complete_ratio = parseInt(task.progress_value);
}
```
## 2. Weighted Progress Mode
This mode allows assigning different weights to subtasks to reflect their relative importance in the overall task or project progress.
**Implementation:**
- Enabled by setting `use_weighted_progress` to true in the project settings
- Weights are updated through the `on-update-task-weight.ts` socket event handler
- The UI shows a weight input for subtasks in the task drawer
- Default weight is 100 if not specified
**Calculation Logic:**
- Progress is calculated using a weighted average: `SUM(progress_value * weight) / SUM(weight)`
- This gives more influence to tasks with higher weights
- A parent task's progress is the weighted average of its subtasks' progress
**Code Example:**
```typescript
// Weight update via socket.io
socket?.emit(SocketEvents.UPDATE_TASK_WEIGHT.toString(), JSON.stringify({
task_id: task.id,
weight: value,
parent_task_id: task.parent_task_id
}));
```
## 3. Time-based Progress Mode
This mode calculates progress based on estimated time vs. actual time spent.
**Implementation:**
- Enabled by setting `use_time_progress` to true in the project settings
- Uses task time estimates (hours and minutes) for calculation
- No separate socket handler needed as it's calculated automatically
**Calculation Logic:**
- Progress is calculated using time as the weight: `SUM(progress_value * estimated_minutes) / SUM(estimated_minutes)`
- For tasks with time tracking, estimated vs. actual time can be factored in
- Parent task progress is weighted by the estimated time of each subtask
**SQL Example:**
```sql
WITH subtask_progress AS (
SELECT
CASE
WHEN manual_progress IS TRUE AND progress_value IS NOT NULL THEN
progress_value
ELSE
CASE
WHEN EXISTS(
SELECT 1
FROM tasks_with_status_view
WHERE tasks_with_status_view.task_id = t.id
AND is_done IS TRUE
) THEN 100
ELSE 0
END
END AS progress_value,
COALESCE(total_hours * 60 + total_minutes, 0) AS estimated_minutes
FROM tasks t
WHERE t.parent_task_id = _task_id
AND t.archived IS FALSE
)
SELECT COALESCE(
SUM(progress_value * estimated_minutes) / NULLIF(SUM(estimated_minutes), 0),
0
)
FROM subtask_progress
INTO _ratio;
```
## Default Progress Tracking (when no special mode is selected)
If no specific progress mode is enabled, the system falls back to a traditional completion-based calculation:
**Implementation:**
- Default mode when all three special modes are disabled
- Based on task completion status only
**Calculation Logic:**
- For tasks without subtasks: 0% if not done, 100% if done
- For parent tasks: `(completed_tasks / total_tasks) * 100`
- Counts both the parent and all subtasks in the calculation
**SQL Example:**
```sql
-- Traditional calculation based on completion status
SELECT (CASE
WHEN EXISTS(SELECT 1
FROM tasks_with_status_view
WHERE tasks_with_status_view.task_id = _task_id
AND is_done IS TRUE) THEN 1
ELSE 0 END)
INTO _parent_task_done;
SELECT COUNT(*)
FROM tasks_with_status_view
WHERE parent_task_id = _task_id
AND is_done IS TRUE
INTO _sub_tasks_done;
_total_completed = _parent_task_done + _sub_tasks_done;
_total_tasks = _sub_tasks_count + 1; -- +1 for the parent task
IF _total_tasks = 0 THEN
_ratio = 0;
ELSE
_ratio = (_total_completed / _total_tasks) * 100;
END IF;
```
## Technical Implementation Details
The progress calculation logic is implemented in PostgreSQL functions, primarily in the `get_task_complete_ratio` function. Progress updates flow through the system as follows:
1. **User Action**: User updates task progress or weight in the UI
2. **Socket Event**: Client emits socket event (UPDATE_TASK_PROGRESS or UPDATE_TASK_WEIGHT)
3. **Server Handler**: Server processes the event in the respective handler function
4. **Database Update**: Progress/weight value is updated in the database
5. **Recalculation**: If needed, parent task progress is recalculated
6. **Broadcast**: Changes are broadcast to all clients in the project room
7. **UI Update**: Client UI updates to reflect the new progress values
This architecture allows for real-time updates and consistent progress calculation across all clients.
## Associated Files and Components
### Backend Files
1. **Socket Event Handlers**:
- `worklenz-backend/src/socket.io/commands/on-update-task-progress.ts` - Handles manual progress updates
- `worklenz-backend/src/socket.io/commands/on-update-task-weight.ts` - Handles task weight updates
2. **Database Functions**:
- `worklenz-backend/database/migrations/20250423000000-subtask-manual-progress.sql` - Contains the `get_task_complete_ratio` function that calculates progress based on the selected method
- Functions that support project creation/updates with progress mode settings:
- `create_project`
- `update_project`
3. **Controllers**:
- `worklenz-backend/src/controllers/project-workload/workload-gannt-base.ts` - Contains the `calculateTaskCompleteRatio` method
- `worklenz-backend/src/controllers/projects-controller.ts` - Handles project-level progress calculations
- `worklenz-backend/src/controllers/tasks-controller-base.ts` - Handles task progress calculation and updates task view models
### Frontend Files
1. **Project Configuration**:
- `worklenz-frontend/src/components/projects/project-drawer/project-drawer.tsx` - Contains UI for selecting progress method when creating/editing projects
2. **Progress Visualization Components**:
- `worklenz-frontend/src/components/project-list/project-list-table/project-list-progress/progress-list-progress.tsx` - Displays project progress
- `worklenz-frontend/src/pages/projects/project-view-1/taskList/taskListTable/taskListTableCells/TaskProgress.tsx` - Displays task progress
- `worklenz-frontend/src/pages/projects/projectView/taskList/task-list-table/task-list-table-cells/task-list-progress-cell/task-list-progress-cell.tsx` - Alternative task progress cell
- `worklenz-frontend/src/components/task-list-common/task-row/task-row-progress/task-row-progress.tsx` - Displays progress in task rows
3. **Progress Input Components**:
- `worklenz-frontend/src/components/task-drawer/shared/info-tab/details/task-drawer-progress/task-drawer-progress.tsx` - Component for inputting task progress/weight
## Choosing the Right Progress Method
Each progress method is suitable for different types of projects:
- **Manual Progress**: Best for creative work where progress is subjective
- **Weighted Progress**: Ideal for projects where some tasks are more significant than others
- **Time-based Progress**: Perfect for projects where time estimates are reliable and important
Project managers can choose the appropriate method when creating or editing a project in the project drawer, based on their team's workflow and project requirements.